Expectation of less time needed for this project based on the level of detail available to date (probably can be reduced to 12 weeks).
Rough shops/model (2-3 weeks)
• Issues and coordination (3-4 weeks)
• Highly dependent on project type and detail of specifications
• Material submittals can run concurrent with coordination
• Revision of shops for prototype construction (1 week)
• Prototype construction (4-6 weeks)
• Includes material procurement and construction
• Prototype review (2 weeks)
• Final shops drawings (1 week)
• Shop drawing review/approval (2 weeks)
• Total minimum duration 15-19 weeks typical